Work continues in multiple buildings across the site. Interior demolition is finished in buildings C, D, F, and H. Interior abatement is nearing completion in buildings C and H. Buildings on the southern half of the site are currently being prepped in anticipation of work that will start as buildings in the north reach completion. Barging will take place the week of April 28th to remove demolition debris.

The art conservation firms have made significant process with the three WPA era murals. The Ilya Bolotowsky mural canvas has successfully been separated from the wall. Removal of the Albert Swinden and Joseph Rugolo murals is ongoing and will be complete in early May. After leaving Goldwater, the murals will travel to conservation studios where restoration will begin.

The U.S. Geological Survey is in the process of taking final geothermal readings. Once complete, the data will determine the viability of a geothermal well field and ultimately guide the design.

Air quality monitoring data is available on the Cornell Tech construction website.