Interior demolition is fully complete in all Phase 1 buildings (the northern portion of site). Interior abatement is ongoing, although this work is fully complete in building C. The work zone has expanded into Phase 2 buildings (the southern portion of site), with interior demolition starting in buildings A and B.

The art conservation firms have successfully removed the three WPA murals from Goldwater Hospital. They have fully demobilized and vacated the site. The murals are now going to the firms’ art studios in Manhattan for a more thorough assessment of canvas and paint conditions, to be followed by conservation work.

Data from the Community Air Monitoring Program has been shared on the construction website. Daily average and daily maximum particulate concentrations are included, along with action levels.