Interior demolition and interior abatement are progressing well across the site. Interior demolition is complete in all but two buildings (Building B and E). The interior abatement crews are currently spread across four buildings. They have completed the abatement work on the Building C roof. The regulatory agencies that are involved in the project have requested that the contractor perform some additional work at this time in advance of structural demolition. As a result, small crews have remobilized and returned to Phase 1 (Building D and F).

The weather station has been removed from the roof of Building J. Consultants will soon begin to analyze the data to develop a comprehensive understanding of weather conditions and wind patterns at the site.

The transition to the new barging operator has been seamless. They have successfully made multiple trips to Roosevelt Island to remove waste and deliver empty containers. The next barge trip will likely take place late in the week of June 9th.