Work has begun on Building D, the last building standing in Phase I. Façade demolition is complete and structural demolition by mechanical means is ongoing. Work on the building will be complete later this month, at which point the contractors will begin removing the foundations of buildings D, F, and H.

In the next two weeks, demolition work will begin on buildings G and J in Phase II. This will alleviate congestion on site and create two additional circulation corridors within the site. As part of easing logistics, the construction trailers will be relocated to the east side of the site.

Early infrastructure work along the west roadway is slated to start by the end of the month. The work will include installation of a new ductbank and relocation of a water line. We are currently working with contractors to develop logistics plans and finalize work plans.