Roadwork and Central Utility Plant – Roadway work is occurring along the north transverse road with water line, sewer pipe and manhole installation taking place. Also at the north transverse road, Boiler-matic work will be occurring in preparation for the turnover on Saturday, 25 July. Work is also taking place on the east road with sewer, storm, and electrical utilities installation ongoing.

Co-Location Building – Excavation and foundation work is ongoing. This includes drilling rock anchors.

Residential Building – Site Preparation is still ongoing in the form of surveying and perimeter erosion control. Excavation for foundations is underway. Slabs and interior footings are also occurring.

Bloomberg Center – Basement Slab forming is ongoing with installation of utility chases and utilities happening concurrently.  Basement foundation walls in the south section of the building is ongoing.