Roadwork and Central Utility Plant – Work inside the Central Utility Plant continues with mechanical fit out and painting of the transformer vaults.  Primary electrical distribution at the main feed from the street is underway.  On the roof, screen wall posts are being installed and grouted in place.  Roof flashing work is also ongoing. Enclosures for the rooftop mechanical units will be installed toward the end of this period.  In the vault, cable racks and conduit installation work is ongoing.  Utility infrastructure continues in the West Loop Road.

Co-Location Building – At CoLo, the first floor deck is being poured in the beginning of this period.  Spray on fireproofing will also commence at the basement level.  Steel erection continues and is currently on the 6th floor.

Residential Building – The superstructure will reach the 25th floor by the middle of the second week and form work will be underway for the 26th floor by the end of the period.  Masonry in the interior continues as does mechanical and electrical sleeve installation throughout.  Drywall for the Residential Building is being delivered via barge.

Bloomberg Center –At the Bloomberg Center, temporary lighting is being installed on the 3rd floor. Primary steel for the photo voltaic panel system is underway and will continue through this period.  The second floor concrete deck will be prepped and poured in this period, and prep work for the 3rd floor deck will commence towards the end of the second week.  Spray on fireproofing in the cellar will begin in this period.