Roadwork and Central Utility Plant – Installation of Foam Glass on the exterior masonry of the Central Utility Plant (CUP) will continue through this period. Pavers in the equipment maintenance area on the CUP roof are being installed through this period. Commissioning of electrical and mechanical systems is ongoing in the Central Utility Plan (CUP). Additional finish work in the CUP includes drywall in the Distributed Generation room. Concrete curb and sidewalk installation continues on the south side of the South Loop Road. Curb work on the East Road is ongoing. Paver installation on the NE and NW corners of the North Road will be complete in this period. Stormwatert filtration and bioinfiltration systems at the Bridge (CoLo) and the Residential Building will begin in this period. Excavation for the Bloomberg Café Terrace retaining wall will also commence during this period. Grading of landforms in Phase 2 is ongoing.

Geothermal – Flushing of the geothermal piping system will commence during this period as the geothermal system begins to come on line in the coming weeks. Commissioning is scheduled to continue through October.

Co-Location Building – Glass curtain wall continues to be installed on the east and west sides of the building. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing. Drywall installation is underway and will continue throughout the building. The vapor barrier on the roof continues to be installed.

Residential Building – At the Residential Building, caulking on the north and east face is ongoing. Air barrier installation is ongoing on multiple floors.  Installation of the roofing main barrier is ongoing. Framing apartments continues on the upper floors and drywall installation is following closely behind.

Bloomberg Center – Halo (PV level) Façade panel installation will continue on the west side of the building in the first week of the period and move to the north façade in the second week of the period. Additional work on the exterior includes welding of clips on Stair 5 in order to receive panels and glass. Soffit work along the exterior façade is also underway.  Roofing installation on the main section of the roof is ongoing.