Sitework and Central Utility Plant – For site work, grading of the interim landscape continues in the phase 2 area of campus. Retaining wall rebar and formwork continues at the southwest corner of the Bloomberg Center. Pending review and acceptance of a mockup by the Design Team, the wall likely will be completed by the end of the period. Precast seatwall installation on the west side of the Bridge (Co-Location Building) is underway and work in this area will be continue into January of 2017. Sidewalk installation continues along East Loop Road.

Geothermal – HVAC system commissioning is ongoing and work continues on the BMS controls interface.

Co-Location Building –Soffit work is ongoing on the two main cantilevers. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing.  Elevator work is ongoing and is nearing completion. The construction hoist will be demobilized and fill in glass curtain wall work will commence towards the end of this period. Drywall installation is underway and will continue throughout the building.

Residential Building – At the Residential Building, the elevator hoist will be demobilized in the beginning of this period. Once removed, the remaining façade panels will be installed and caulking complete on the south façade. Cabinets will be installed on floors 24 and 25. Wood floor installation will begin on floors 17 through 19. Shoemolding will commence on floors 5 through 8. Installation of the storefront (glass and metal frame) will continue through this period.

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Interior framing and MEP work continues on all floors. Painting of steel at Stair 5 is underway and will be complete in this period.