Cornell Tech's Roosevelt Island Campus Construction

Information and updates for the Roosevelt Island community

Author: Manuel Calimlim

Air Quality Monitoring April 14

Icon Air Quality Monitoring April 14 (354.3 KB)

March 13 – March 24 Look Ahead

Sitework and Central Utility Plant – At the Central Utility Plant (CUP), FDNY inspection is scheduled for the end of this period. The last remaining façade panels are scheduled to be delivered and installed. Additionally, the green roof system on the CUP will be prepped for installation following the removal of the Residential Building overhead protection. Concrete work at the Outdoor Classroom on the east side of the Bridge continues. Footings and rough grade between the Bridge and Residential Building is underway.The Campus Lawn area is being cleared and prepped for horticultural soils that should begin by the end of the period. Pathway curb edging and trench drains will begin at Campus Lawn and on the south side of the Bridge.

Co-Location Building – Soffit work on the exterior continues at the Bridge. Replacement glass panels are being installed in this period. Vertical gutters at the west atrium will be installed during this period. Fit out of the Cornell Tech space continues. MEP work on all floors is ongoing. Photovoltaic struts and panel installation is underway on the roof.

Residential Building – At the Residential Building, storefront work continues. The last remaining façade panels in the hoist way will be placed towards the end of this period. Fitout and finishes continue on all floors and includes plumbing work in apartments i.e. dishwasher connections, bathroom facilities in apartments.

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Curved glass panel installation is underway at Stair 5. Interior framing and MEP work continues on all floors.