Roosevelt Island Campus Project

Menu

Construction Updates

Clear filter

Icon Air Quality Monitoring April 14 (354.2 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring March 31 (355.2 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring March 10 (356.1 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring February 17 (354.4 KB)

Tagged:  Project Updates

Sitework and Central Utility Plant – At the Central Utility Plant (CUP), FDNY inspection is scheduled for the end of this period. The last remaining façade panels are scheduled to be delivered and installed. Additionally, the green roof system on the CUP will be prepped for installation following the removal of the Residential Building overhead protection. Concrete work at the Outdoor Classroom on the east side of the Bridge continues. Footings and rough grade between the Bridge and Residential Building is underway.The Campus Lawn area is being cleared and prepped for horticultural soils that should begin by the end of the period. Pathway curb edging and trench drains will begin at Campus Lawn and on the south side of the Bridge. 

Co-Location Building – Soffit work on the exterior continues at the Bridge. Replacement glass panels are being installed in this period. Vertical gutters at the west atrium will be installed during this period. Fit out of the Cornell Tech space continues. MEP work on all floors is ongoing. Photovoltaic struts and panel installation is underway on the roof. 

Residential Building – At the Residential Building, storefront work continues. The last remaining façade panels in the hoist way will be placed towards the end of this period. Fitout and finishes continue on all floors and includes plumbing work in apartments i.e. dishwasher connections, bathroom facilities in apartments.

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Curved glass panel installation is underway at Stair 5. Interior framing and MEP work continues on all floors.

Icon Air Quality Monitoring February 3 (356.2 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring January 13 (355.7 KB)

Tagged:  Project Updates

Sitework and Central Utility Plant – Testing, Inspections, and commissioning of electrical, mechanical, and life safety systems are ongoing at the Central Utility Plant (CUP). For site work, grading of the interim landscape continues in the phase 2 area of campus. Barging of horticultural soils will continue through the end of this period. Backfilling will commence behind the Bloomberg Center Café Terrace retaining wall. The recreation terrace and stair on the south side of the Bridge will be formed and prepped for pouring in this period. The Granite Paver concrete base slab at the “Gateway” will be prepped and poured in this period. Sidewalk installation continues on the South Road in this period. 

Co-Location Building – Waterproof membrane installation will begin on the southern part of the west terrace. Glass on the first floor will be installed at the hoist location. Soffit work is ongoing on the two main cantilevers. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing. Drywall installation continues throughout the building. 

Residential Building – At the Residential Building, installation of the façade panels in the hoistway continues. Shoemolding installation will begin on floors 17 and 18.  Wood floor installation will continue on floors 21 and 22 and begin on 23. Storefront work continues. 

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Additional exterior work will include the installation of panels at the load in area on the west side. Interior framing and MEP work continues on all floors.

Sitework and Central Utility Plant – Testing, Inspections, and commissioning of electrical, mechanical, and life safety systems are ongoing at the Central Utility Plant (CUP). For site work, grading of the interim landscape continues in the phase 2 area of campus. Barging of horticultural soils will continue through the end of January. The retaining wall at the southwest corner of the Bloomberg Center will be poured during this period. Precast seatwall foundation installation on the west side of the Bridge (Co-Location Building) continues concurrently with other underground infrastructure in the area. Sidewalk installation continues on the South Road in this period. 

Co-Location Building –Soffit work is ongoing on the two main cantilevers. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing. Drywall installation is underway and will continue throughout the building. 

Residential Building – At the Residential Building, installation of the façade panels in the hoistway will commence. Shoemolding installation will begin on floors 14 through 16. Wood floor installation is ongoing in floors 21 and 22. Storefront work continues. 

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Additional exterior work includes prepping of all cantilevered terraces for waterproofing and the installation of anchors at Stair 5 in preparation for glass façade installation. Interior framing and MEP work continues on all floors.