Roosevelt Island Campus Project

Menu

Construction Updates

Clear filter

Icon Air Quality Monitoring December 30 (355.6 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring December 16 (354.3 KB)

Tagged:  Project Updates

Sitework and Central Utility Plant – At the Central Utility Plant (CUP), base flashing will be installed on the west façade. Additional exterior work will include the installation of the final metal façade panels on the north façade. For site work, grading of the interim landscape continues in the phase 2 area of campus. In the second week of the period, horticultural soils will be barged in and installed in the phase 2 area. The retaining wall at the southwest corner of the Bloomberg Center will be poured during this period. Precast seatwall foundation installation on the west side of the Bridge (Co-Location Building) continues concurrently with other underground infrastructure in the area. Sidewalk installation will begin along the west road towards the end of the period. 

Co-Location Building – With the hoist way removed, final façade curtain wall installation will begin in this period.  Glass panel installation will be complete within the period and caulking and final trim will continue into February. Soffit work is ongoing on the two main cantilevers. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing. Drywall installation is underway and will continue throughout the building. 

Residential Building – At the Residential Building, the loading dock will be removed in this period as façade panel installation at the hoist way area commences. Base and trim work is underway on the 25th floor. Shoemolding installation will begin on floors 10 through 13. Wood floor installation is ongoing in floors 17 through 20. Storefront work continues. 

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Additional exterior work includes prepping of all cantilevered terraces for waterproofing and the installation of anchors at Stair 5 in preparation for glass façade installation. Interior framing and MEP work continues on all floors.  

Icon Air Quality Monitoring December 2 (356.4 KB)

Tagged:  Project Updates

Sitework and Central Utility Plant – For site work, grading of the interim landscape continues in the phase 2 area of campus. Retaining wall rebar and formwork continues at the southwest corner of the Bloomberg Center. Pending review and acceptance of a mockup by the Design Team, the wall likely will be completed by the end of the period. Precast seatwall installation on the west side of the Bridge (Co-Location Building) is underway and work in this area will be continue into January of 2017. Sidewalk installation continues along East Loop Road. 

Geothermal – HVAC system commissioning is ongoing and work continues on the BMS controls interface. 

Co-Location Building –Soffit work is ongoing on the two main cantilevers. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing.  Elevator work is ongoing and is nearing completion. The construction hoist will be demobilized and fill in glass curtain wall work will commence towards the end of this period. Drywall installation is underway and will continue throughout the building. 

Residential Building – At the Residential Building, the elevator hoist will be demobilized in the beginning of this period. Once removed, the remaining façade panels will be installed and caulking complete on the south façade. Cabinets will be installed on floors 24 and 25. Wood floor installation will begin on floors 17 through 19. Shoemolding will commence on floors 5 through 8. Installation of the storefront (glass and metal frame) will continue through this period. 

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Interior framing and MEP work continues on all floors. Painting of steel at Stair 5 is underway and will be complete in this period.

 

Sitework and Central Utility Plant – For site work, grading of the interim landscape continues in the phase 2 area of campus. Retaining wall rebar and formwork continues at the southwest corner of the Bloomberg Center. Precast seatwall installation at the Northwest Corner (Gateway) is underway and will be complete in this period. Sidewalk installation continues along East Loop Road. 

Geothermal – HVAC system commissioning is ongoing and work continues on the BMS controls interface. 

Co-Location Building –Soffit work is ongoing on the two main cantilevers. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing. Elevator work is ongoing and is nearing completion. Inspection for the elevator is scheduled to occur by the end of the period. Once approved, the construction hoist will be demobilized and fill in glass curtain wall work will commence.  Drywall installation is underway and will continue throughout the building. 

Residential Building – At the Residential Building, caulking on the south face will continue into December. Waterproofing work on the 26th and 27th floors will continue in this period. Cabinets will be installed on floors 21 through 23. Wood floor installation will begin on floors 13 through 16.  Installation of the storefront (glass and metal frame) will continue through this period. 

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Interior framing and MEP work continues on all floors.

Roadwork and Central Utility Plant – At the Central Utility Plant (CUP) roof paver installation is underway. And coping on the west and north elevation will be complete in the beginning of this period. Exterior doors will be installed on the north façade. Finish work and commissioning continues on the interior and with the CUP MEP systems. For site work, grading of the interim landscape continues in the phase 2 area of campus. Retaining wall rebar and formwork continues at the southwest corner of the Bloomberg Center. Precast seatwall preparation will begin in the second week of the period. Sidewalk installation continues along East Loop Road. 

Geothermal – HVAC system commissioning is ongoing and work continues on the BMS controls interface.  

Co-Location Building –Soffit work is ongoing on the two main cantilevers. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing. Drywall installation is underway and will continue throughout the building. Waterproofing of the garage roof deck will occur in this period concurrent with layout and installation of dowels for precast seatwall footing connections.

Residential Building – At the Residential Building, caulking on the south face will continue into December. Waterproofing will be installed on the 26th and 27th floors. Cabinets will be installed on floors 17 through 20.  Wood floor installation will begin on floors 10 through 13. Installation of the storefront (glass and metal frame) will begin in this period. 

Bloomberg Center – Soffit work and roofing continue on the exterior of the Bloomberg Center. Interior framing and MEP work continues on all floors.

Icon Air Quality Monitoring November 18 (354.4 KB)

Tagged:  Project Updates

Roadwork and Central Utility Plant – Coping will be installed on the west and north elevations of the Central Utility Plant (CUP) in the first week of this period. Panel installation will continue through this period as well. Sidewalk work will continue on East Loop Road moving to the south. Phase 2 area grading continues throughout this period. Retaining wall footings in the southwest corner of the Bloomberg Center will see installation of formwork and rebar in the first week of this period and will be poured in the second week. Bio-infiltration and filtration zones will be constructed beginning in the first week of the period. Concurrently, site electrical conduit installation will commence in the same area at the end of the second week of the period. 

Geothermal – HVAC system commissioning is ongoing and work continues on the BMS controls interface. 

Co-Location Building –Soffit work is ongoing on the two main cantilevers. Roofing is underway and will continue through November.  Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing. Drywall installation is underway and will continue throughout the building.    

Residential Building – At the Residential Building, caulking on the south face will continue through this period. Air barrier installation is ongoing on multiple floors. Installation of the roofing main barrier is ongoing. Framing apartments continues on the upper floors and drywall installation is following closely behind. Cabinets will be installed on floors 14, 15, 16, and 17 throughout the two week period.

Bloomberg Center – Façade panel installation will be complete on the north side of the building in the second week of the period. Work at Stair 5 continues as the framing connections for the window system are being installed. Soffit work along the exterior façade is also underway.  Roofing installation on the main section of the roof is ongoing.

Icon Air Quality Monitoring November 4 (354.7 KB)

Tagged:  Project Updates