Roadwork and Central Utility Plant – Stainless Steel façade panels are being installed on the north face of the Central Utility Plant (CUP). Deliveries and installation of panels is scheduled to occur over the next several weeks. Painting of the interior continues in the CUP.  The fuel oil fill box and vent piping will be installed in this period. Paving of East Loop Road and North Loop Road will begin in the second week of this period. Sidewalks along the northeast side of the campus will be formed and poured in this period. Phase 2 area grading continues throughout this period. Retaining wall footings in the southwest corner of the Bloomberg Center are being excavated and prepped for forming.   

Geothermal – Factory startup of the multistack systems and the pumping systems is complete. The chilled water startup of the multistack will be fully commissioned in the spring/summer of 2017. BMS system commissioning and point to point check out is ongoing. 

Co-Location Building – Glass curtain wall continues to be installed on the east and west sides of the building. Soffit work is ongoing on the two main cantilevers. Roofing is underway and will continue through November. Mechanical, electrical, and plumbing (MEP) rough in continues throughout the building as does interior framing. Drywall installation is underway and will continue throughout the building.    

Residential Building – At the Residential Building, caulking on the south face will begin in this period. Air barrier installation is ongoing on multiple floors. Installation of the roofing main barrier is ongoing. Framing apartments continues on the upper floors and drywall installation is following closely behind.

Bloomberg Center – Façade panel installation will move to the north side of the building in the beginning of the period. Work at Stair 5 continues as the framing connections for the window system are being installed. Soffit work along the exterior façade is also underway.  Roofing installation on the main section of the roof is ongoing.

Tagged:  Project Updates

Icon Air Quality Monitoring October 21 (354.4 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring October 7 (354.7 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring September 23 (354.6 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring September 9 (357.6 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring, August 26 (352.6 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring August 12 (352.6 KB)

Tagged:  Project Updates

Icon Air Quality Monitoring July 29 (351.9 KB)

Tagged:  Project Updates